
Associate
Commercial Energy | Energy & Infrastructure | Projects, Infrastructure & Construction
This website will offer limited functionality in this browser. We only support the recent versions of major browsers like Chrome, Firefox, Safari, and Edge.
By Greg Humphries, Melissa Story
16 Jan 2025 | 4 minute readThe recent decision offers a powerful new tool for contractors to terminate JCT contracts when faced with non-payment…
The unanimous decision of the Court of Appeal ('CA') in Providence Building Services Limited v Hexagon Housing Association Limited has provided clarity on a contractor's entitlement to terminate the JCT Design & Build 2016 (D&B) Contract (‘the Contract’) for repeated specified breaches.
The case concerned multiple late payments by the employer, Hexagon Housing Association Limited ('Hexagon'). The contractor, Providence Building Services Limited ('Providence'), issued a specified default notice for the first non-payment by the due date, which Hexagon remedied within the relevant cure period. However, a failure to pay on time under a subsequent payment notice meant Providence sought to terminate, by serving notice to Hexagon pursuant to Clause 8.9.4 of the Contract, for repeated breach of the specified default.
The decision hinged on the interpretation of Clauses 8.9.3 and 8.9.4 of the Contract, with the CA concluding that a contractor does not need to accrue a right to terminate under Clause 8.9.3 before being able to exercise its termination rights under Clause 8.9.4. Please see this clause in further detail below:
Default by Employer
8.9.1 If the Employer:
.1 does not pay by the final date for payment the amount due to the Contractor in accordance with clause 4.9 and/or any VAT properly chargeable on that amount […] the Contractor may give to the Employer a notice specifying the default or defaults (a ‘specified’ default or defaults).
8.9.3 If a specified default or a specified suspension event continues for 28 days* from the receipt of notice under clause 8.9.1 or 8.9.2, the Contractor may on, or within 21 days from, the expiry of that 28 day** period by a further notice to the Employer terminate the Contractor’s employment under this Contract.
8.9.4 If the Contractor for any reason does not give the further notice referred to in clause 8.9.3, but (whether previously repeated or not):
.1 the Employer repeats a specified default; [… ] then, upon or within 28 days*** after such repetition, the Contractor may by notice to the Employer terminate the Contractor’s employment under this Contract.”
* standard wording "14 days"
** standard wording "14 days"
*** standard wording "a reasonable time"
The CA determined that the wording in Clause 8.9.4 "if for any reason [Providence] does not give the further notice referred to in clause 8.9.3" was sufficiently broad to allow termination where a specified breach is repeated (e.g., late payment), even if the initial breach was remedied within the cure period meaning that the option under Clause 8.9.3 was never available. This interpretation underscores the clause's purpose: to encourage compliance with contractual obligations and provide the wronged party with an enforceable and immediate remedy for repeated breaches.
It is unlikely that this ruling will result in a floodgate of contractors exercising termination powers under Clause 8.9.4 at the first viable opportunity. Termination remains the nuclear option, has the potential to damage relationships and standing within the construction industry, and could give rise to further disputes as to its validity in any event. A contractor seeking to terminate a funded project may also encounter the added complication of a funder exercising its step-in rights.
Notwithstanding the parties' bespoke amendments in this case as to the specified timeframes under clause 8.9 of the Contract, this decision is likely to have a determinative effect on the relevant termination provisions of the ubiquitous JCT Design & Build Contract 2016, as well as other contracts within the JCT suite.
While the ruling empowers contractors, it underscores the need to:
At Foot Anstey, our construction team regularly advises on JCT contracts and their practical application. If you would like to discuss the implications of this ruling, or require assistance with construction contracts or dispute resolution, please do get in touch with our team of experts.